RPL Refinery project ahead of schedule
Mumbai, Reliance Petroleum Limited ("RPL") has set a blistering pace on all implementation fronts and achieved over 70% overall progress in implementation of its large and complex refinery, coming up in a Special Economic Zone at Jamnagar.
- No files attached
Reliance Petroleum Limited ("RPL") has set a blistering pace on all implementation fronts and achieved over 70% overall progress in implementation of its large and complex refinery, coming up in a Special Economic Zone at Jamnagar. Based on the progress made till date, in the engineering, procurement and construction activities, RPL expects to complete the project ahead of December 2008.
During the quarter, project implementation gained further momentum and led to achievement of several significant milestones.
Engineering is nearing completion with all drawings for concreting, structural steel and underground piping and over 90% of electrical and instrumentation released for construction. This phenomenal engineering progress achieved within a short span of 22 months reflects the success of a massive team effort that involved over 7,500 engineers, who worked from several interconnected locations across the world.
Procurement progress has been equally impressive. Procurement and contracting for equipments, tagged items and bulk materials is now complete. There is a barrage of equipment deliveries at site, with over 1,000 equipments, including several critical and long lead heavy equipments delivered during the quarter alone. With this, over 50% of all equipments / tagged items required for the project have already been received at site. Nearly all the bulk materials, including pipes and fittings for the project as well as substantial part of electrical and instrumentation bulks have also been delivered at site.
The construction activities have also peaked with aggregate volume of concrete poured at the project site crossing the 1.5 million cubic meter mark during the quarter. Most of the civil work is complete.
Commenting on the project progress Mr Mukesh Ambani, Chairman of Reliance Petroleum said "I would like to compliment the entire RPL team on the remarkable progress made so far and preparedness for the tasks ahead. The team is fully geared up and motivated to commission the refinery ahead of its initial schedule of December 2008. RPL is poised to create a new world record for project implementation in the refining sector".
Please visit www.reliancepetroleum.com for a photo preview of project progress at the site
- End -